Zenith was contacted by Shell UK Limited, who operates several offshore platforms in the North Sea, to change out the top vertical section (max 2.5Te lifts) on three of their lifeboat stations and to install new lifeboats. The project presented two key problems:
Firstly, the offshore platform crane could not reach the area where the lifeboat stations were located and secondly, the access to and around the stations proved extremely tight for manoeuvrability of necessary plant, equipment and the newly fabricated vertical sections. The client considered using temporary mobile cranes, additional lifting points and how to utilize scaffolding to allow the crane suitable access, however, this solution would prove onerous due to the load bearing on the platform. An alternative solution had to be found. Zenith proposed the following NINE step solution to the client, which was duly considered and accepted.
STEP 1 – Initial Concept Design
STEP 2 – Full Design Works
STEP 3 – Fabrication and Testing of Equipment
STEP 4 – Project Management of Site Works
STEP 5 – Offshore Pre-Outage Works:
STEP 6 – Replace First Lifeboat
STEP 7 – Replace Second Lifeboat
STEP 8 – Replace Third Lifeboat
STEP 9 – Offshore Post-Outage Works